Measure how effectively available production capacity is being used. Calculate capacity utilisation, production efficiency, output shortfall, idle capacity and the estimated cost of unused operating time.
1. Production Capacity
2. Production Output
Calculate Production Efficiency
Reset
Capacity and Efficiency Results
Production Analysis
Formulas:
Capacity utilisation = actual operating hours ÷ available production hours × 100.
Production efficiency = actual output ÷ (actual operating hours × standard output per hour) × 100.
Plan attainment = actual output ÷ planned output × 100.
Idle hours = available hours − operating hours.
Estimated idle-capacity cost = idle hours × cost per available hour.
Capacity utilisation measures how much available time was used. Production efficiency measures how much output was achieved during the time actually operated. Plan attainment compares actual production with the target. These measures are different and should not be interpreted interchangeably.
Example Reference
The figures below are illustrative only. They are not entered automatically into the calculator.
Example results:
Capacity utilisation = 1,600 ÷ 2,000 × 100 = 80%.
Standard output for actual operating hours = 1,600 × 50 = 80,000 units.
Production efficiency = 70,000 ÷ 80,000 × 100 = 87.5%.
Idle capacity = 2,000 − 1,600 = 400 hours.
If the cost per available hour is ₹1,500, estimated idle-capacity cost = 400 × ₹1,500 = ₹6,00,000.
Assumptions: Available and operating hours refer to the same production resources and period. The standard production rate is assumed to be comparable with actual output. The idle-capacity cost is an estimate, not necessarily an avoidable cash cost or a measure of lost profit.